Production

Production Output Up 24 Percent

Production output in all divisions with the exception of Siltronic rose in 2011 compared with the previous year. Capacity utilization at our chemical divisions was in excess of 80 percent. There were no unplanned facility shutdowns. At Siltronic, we reduced all production lines on a day-by-day basis in the fourth quarter due to weaker demand. Production costs rose 24 percent while production output climbed 10 percent.

  download table

Capacity Utilization in 2011

%

 

Plant Utilization

 

 

 

WACKER POLYSILICON

 

84

WACKER SILICONES

 

84

WACKER POLYMERS

 

96

SILTRONIC

 

74

Investments in new manufacturing plants amounted to €922.7 million in 2011. Most funds flowed into the expansion of our polysilicon facilities. Production ramp-up at Nünchritz started in the third quarter and construction of a new polysilicon site in the US State of Tennessee began in April 2011. WACKER SILICONES opened its second pyrogenic-silica manufacturing facility in Zhangjiagang, China. The Kempten site, where pyrogenic silica had been produced, was closed in mid-August as planned. Production will continue at Burghausen and Nünchritz.

  download table

Key Start-Ups

Site

 

Project

 

Start-Up

 

 

 

 

 

Nünchritz

 

Poly 9 expansion stage

 

2011

Zhangjiagang

 

HDK® plant 2

 

2011

Zhangjiagang

 

Expansion of silicone sealants

 

2011

Nanjing

 

Merchant dispersions

 

2011

Burghausen

 

Expansion of 300 mm epitaxial wafer capacity

 

2011

Our own Corporate Engineering teams are responsible for running all investment projects. The planning group in the USA was further expanded due to our large-scale project in Tennessee.

More than 500 Productivity Projects Completed

High productivity throughout the supply chain is a key to WACKER’s success. WACKER boosts productivity along the entire supply chain via its Wacker Operating System (WOS) program. Our goal is to continue to reduce specific operating costs every year. WACKER carried out more than 500 projects relating to its operations and corporate departments in 2011.

Productivity Projects According to Focus Productivity Projects According to Focus (bar chart)

Our WOS Academy (founded in 2009) trained almost 100 employees in the application of new productivity methods such as Six Sigma during the year under review.

The standardization of global engineering processes was advanced. We are standardizing and optimizing core engineering processes using international multidisciplinary teams of specialists (plant, mechanical and I&C engineering, and maintenance).